February 2016

Report Date
February 2016

Achievements in Last Period

  • The project scope was changed in Q4 2015 to include the piloting of the documents as part of UAT. However, the project sponsor has been unable to find an MVM unit with the availability to do this. Accordingly, the project will descope this, and instead have the documents checked and QA'd by the existing stakeholders who contributed to the analysis. After accpetance, and before we can close project, the project needs to put in place an on-going document review and maintanenance process.

Issues

  • no medium or high risks

Next Steps

  • resource Elaine again and contact stakeholders

Milestones

31-Mar-2016Single Document Set - Accepted
31-Mar-2016Process Mapping - Checklist Accepted
14-Apr-2016Post-Project Document Support in Place
28-Apr-2016Closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
30.0 days
Activity this month
0.5 days
Activity this year
17.0 days
Activity to date
28.0 days
Estimate to complete current year
4.0 days
Estimate to complete future years
0.0 days