Report for February 16

Report Date
February 2016

Achievements

Issues

 

Next steps

 

Milestones

28-Mar-2016Feedback survey updates deployment 
04-Apr-2016Development of iteration 3 coursework materials - internal signoff 
11-Apr-2016Deploy iteration 3 coursework materials 
27-Apr-2016Deployment review 
03-May-2016Close 
Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
23.0 days
Activity this month
3.0 days
Activity this year
12.0 days
Activity to date
12.0 days
Estimate to complete current year
11.0 days
Estimate to complete future years
0.0 days