January 2016

Report Date
January 2016

Achievements in the last period

  • We signed off the system design.
  • Development has been progressing as planned.
  • We have began the planning required to extend the scope of SMI012 to include the Cold Fusion Upgrade for the Card System.  This is currently part of SMI015.  We have an estimate for SMI015 and we can save resource spend within the SMI programme by combining the two projects.

Issues

  • No issues

Next steps

  • Clarify the extended scope for the Cold Fusion Upgrades.
  • Sign off the Development environment.
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
100.0 days
Activity this month
16.0 days
Activity this year
43.8 days
Activity to date
43.8 days
Estimate to complete current year
56.2 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation

Not available.