Report for January 2016

Report Date
January 2016

Achievements in Last Period

  • Solution for security issue JIRA-25 agreed awiting implementaion and testing

Issues

  • No new issues

Next Steps

  • Implement solution for security issue
  • Deployment Review
  • Closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
170.0 days
Activity this month
1.0 day
Activity this year
35.0 days
Activity to date
165.0 days
Estimate to complete current year
4.0 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation

Not available.