Report for January 2016
- Report Date
- January 2016
Achievements in Last Period
- Solution for security issue JIRA-25 agreed awiting implementaion and testing
Issues
- No new issues
Next Steps
- Implement solution for security issue
- Deployment Review
- Closure
- Approved budget
- 170.0 days
- Activity this month
- 1.0 day
- Activity this year
- 35.0 days
- Activity to date
- 165.0 days
- Estimate to complete current year
- 4.0 days
- Estimate to complete future years
- 0.0 days