January 2015

Report Date
January 2016

 

Kick-Off meeting held, scope, deliverables and objective of project agreed,

Paul and Maurice working on plan and project brief.

Additional Resourcing to provide skills to Desktop team to be confirmed by Paul.

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation

Not available.