Monthly Progress Report
- Report Date
- January 2016
Achievements
- Re-reviewed the testing completed to date
Confirmed with Mass any work not resolved
Weekly conference calls have been completed and status of issues agreed
Issues
- Replanning taking place to replan milestones budgets and tasks
- Plan is likely to end to the end of June
Next Steps
- Implement any remaining fixes to be received from Archibus/Suppliers
- Remaining functional issues to be resolved and JIRAs fixed
All scenario testing is run
Re-confirm full test scripts for both application and mobile devices based on the defined scenarios
Confirm the remaining Fault Type and associated Repair Type definitions relating to the heating engineers have been agreed
- Weekly conference calls with Mass to ensure progress and targets for the coming weeks to continue throughout the Acceptance Testing period
- Plan full user acceptance testing during March April
- Plan Capacity and Performance Testing to be planned during UAT (in March)
Project Sponsor to approve revised milestones and budget
Milestones
Milestones to replanned and agreed
- Approved budget
- 180.0 days
- Activity this month
- 3.3 days
- Activity this year
- 37.9 days
- Activity to date
- 163.9 days
- Estimate to complete current year
- 52.3 days
- Estimate to complete future years
- 0.0 days