January Report

Report Date
January 2016

Achievements in Last Period

  • Peer Testing JIRA fixes (6,7,8,10,11) now resolved and final Peer testing completed / confirmed
  • Data Source now set up in Dev and tested ready to deploy to test

 

Issues

  • Build review held on 05/01 unable to achieve sign off as data source required, peer testing fixes to resolved and requirement for clarity on course code information to be finalised with Student Systems before agreement to move to Integration.
  • Questions raised about Student data relating to 'withdrawn status' has been confirmed by Students Systems and Moodle Service Manager. Final confirmation on using existing Grouper information on course code to be provided.
  • Provide an overview of any manual processes which will still exist on deployment of TEL025.
  • Review of project effort completed and due to additional work associated with course code impacting the project an additional 8 days has been approved for the project following discussions with Project Sponsor and Programme Manager.
  • Project milestones have been reviewed due to the delays around course code

 

Next Steps

  • Build Sign off
  • Complete Integration testing
  • UAT to commence

 

The project status is AMBER due to delays with clarifying course code information

 

06-Feb-2016Build Complete
13-Feb-2016Integration Complete
10-Mar-2016Acceptance complete
17-Mar-2016Deployment complete
24-Mar-2016Deployment Review complete
31-Mar-2016Closure
Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
58.0 days
Activity this month
6.0 days
Activity this year
44.0 days
Activity to date
48.0 days
Estimate to complete current year
11.0 days
Estimate to complete future years
0.0 days