December 2015

Report Date
December 2015

Achievements in the last period

  • The BRD was approved and work has progressed well on the System Design.
  • We had an initial design review and the group approved the design subject to the changes stated at the meeting.  These changes are underway.

Issues

  • No issues to report.

Next steps

  • Sign off the design and as we had planned, fully estimate the remaining work to take the Staff updates into production.
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
100.0 days
Activity this month
10.9 days
Activity this year
27.8 days
Activity to date
27.8 days
Estimate to complete current year
72.1 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation

Not available.