Project Update

Report Date
December 2015

Achievements 

  • Reviewed testing completed
  • Revised milestones agreed
  • Defined full test script for both application and mobile devices based on the defined scenarios

Issues

  • None

Next Steps

  • Re-review the testing completed
  • Confirm with Mass any work not resolved

  • Re-confirm full test script for both application and mobile devices based on the defined scenarios

  • Confirm the remaining Fault Type and associated Repair Type definitions relating to the heating engineers have been agreed

  • Weekly conference calls with Mass to ensure progress and targets for the coming week to continue throughout the Acceptance Testing period
  • Implement remining fix to be received from Archibus
  • Begin full user acceptance testing after the identified enhancements have been delivered in December/January
  • Capacity and Performance Testing to be planned during UAT in January

Project Sponsor to approve revised milestones

Milestones

DateMilestone
18-Dec-2015 date to be agreedTesting and Enhancements Testing
05-Feb-2016Acceptance / User Acceptance Testing
19-Feb-2016Deploy to Live
04-Mar-2016Live Configuration
18-Mar-2016User Training and Rollout
21-Mar-2016Deployment Signoff Review and Closure
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
180.0 days
Activity this month
2.4 days
Activity this year
34.6 days
Activity to date
160.5 days
Estimate to complete current year
26.8 days
Estimate to complete future years
0.0 days