Progress Report
- Report Date
- November 2015
Achievements
- Mass on site for 2 days to work with Estates to test the system out
- More deliveries have taken place
- All delivered received have been deployed for re-testing
- Revised project budget has been approved by the Project Sponsor and Programme Manager
Issues
- None
Next Steps
Agree revised milestones with Project Team and Project Sponsor
Review the testing completed
Plan the work to be retested and forward to Mass if not resolved
Define full test script for both application and mobile devices based on the defined scenarios
Complete the remaining Fault Type and associated Repair Type definitions relating to the heating engineers
- Weekly conference calls with Mass to ensure progress and targets for the coming week to continue throughout the Acceptance Testing period
- Implement fixes to be received from Archibus
- Undertake more rigorous system testing
- Begin full user acceptance testing after the identified enhancements have been delivered in December
- Capacity and Performance Testing to be planned during UAT in January
Since the Enhancements have been delayed by 1 month, the project has been assigned an overall RAG status of RED due to obtaining further assurance that the new milestones will be met
Additional Budget increased approved and now resolved. Working with Supplier on resolving remaining functional issues
Draft Milestones - Milestones to be agreed by the Project Sponsor
Milestones
Date | Milestone |
18-Dec-2015 | Testing and Enhancements Testing |
05-Feb-2016 | Acceptance / User Acceptance Testing |
19-Feb-2016 | Deploy to Live |
04-Mar-2016 | Live Configuration |
18-Mar-2016 | User Training and Rollout |
21-Mar-2016 | Deployment Signoff Review and Closure |
- Approved budget
- 180.0 days
- Activity this month
- 9.2 days
- Activity this year
- 32.3 days
- Activity to date
- 158.2 days
- Estimate to complete current year
- 21.8 days
- Estimate to complete future years
- 0.0 days