November 2015

Report Date
November 2015

Achievements in last period

  • Options document has been reviewed and work prioritised within the SSP programme. Phase 1 is expected to start in May 15/16. 

Issues

  • Solved issues: there has been a delay to get the options submitted and reviewed as noted in piccl 2. Project is Amber to reflect the delay.

Next Steps

  • Business Lead to sign off the Options document.
  • Close project 

 

04-Dec-2015Finalise Options and Recommendation-Final document
14-Dec-2015Close
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
11.0 days
Activity this month
1.0 day
Activity this year
5.0 days
Activity to date
5.0 days
Estimate to complete current year
1.0 day
Estimate to complete future years
0.0 days