Report for November 2015

Report Date
November 2015

Achievements in Last Period

Project plan and brief is with the project team for agreement. Once agreed will ensure CogBooks are in line with the plan and it can then go for sign off

SMEs have already started work on the updates to current materials

 

Issues

None so far

Next Steps

Project Brief to be signed off

 

Milestones

11-Dec-2015Planning
13-Jan-2016Analytics Configuration Semester 2
13-Jan-2016Update current coursework materials
15-Jan-2016Deploy current coursework materials updates
18-Jan-2016Development of new materials
18-Jan-2016Deploy Analytics Semester 2
22-Jan-2016Deploy new materials
15-Feb-2016Analytics Configuration Semester 1
19-Feb-2016Feedback Survey results updates
22-Feb-2016Deploy Analytics Semester 1
31-Mar-2016Feedback Survey results new materials
11-Apr-2016Deployment review
18-Apr-2016Close
Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
20.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation

Not available.