October 2015
- Report Date
- October 2015
Achievements in last period
- N/a
Issues
Both issues raised in september are still opened, their resolution may result in a future change to the project schedule that would cause the project to become AMBER.
- The two opened issues detailed in https://www.projects.ed.ac.uk/project/hrs084/issues/12 were not addressed during the Sept meeting as expected, due to lack of time.
- Paternity leave process to be and related 'must' requirement still need to be captured : https://www.projects.ed.ac.uk/project/hrs084/issues/14
Next Steps
- Two further meetings in November to complete the sign off of the prioritised requirements and address both above issues .
19-Nov-2015 | Business Requirements Document reviewed and signed off |
30-Nov-2015 | Close |
- Approved budget
- 65.0 days
- Activity this month
- 1.0 day
- Activity this year
- 6.0 days
- Activity to date
- 58.0 days
- Estimate to complete current year
- 7.0 days
- Estimate to complete future years
- 0.0 days