September Monthly Report

Report Date
September 2015

Achievements This Period

  • The Test commit was completed and the warning messages either cleared or considered if action was required in September
  • A data load was required to be run for 1,000 staff. This was needed due to new fields from eRecruitment in 14-15 requiring correction.
  • Following that HR had to correct 50 records before runnning the corrected data for the HESA Return - 2-Oct-15

Issues

  • None

Next Steps

  • HESA will review the University HESA Return
  • Between 15-Oct and 12-Nov HR will handle any Queries from HESA
  • IS Apps will support if required.

Milestones

15-Oct-2015Commit
12-Nov-2015Final Submission
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
60.0 days
Activity this month
1.8 days
Activity this year
4.1 days
Activity to date
46.0 days
Estimate to complete current year
14.3 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation

Not available.