- Report Date
- September 2015
Achievements This Period
- The Test commit was completed and the warning messages either cleared or considered if action was required in September
- A data load was required to be run for 1,000 staff. This was needed due to new fields from eRecruitment in 14-15 requiring correction.
- Following that HR had to correct 50 records before runnning the corrected data for the HESA Return - 2-Oct-15
Issues
Next Steps
- HESA will review the University HESA Return
- Between 15-Oct and 12-Nov HR will handle any Queries from HESA
- IS Apps will support if required.
Milestones
- Approved budget
- 60.0 days
- Activity this month
- 1.8 days
- Activity this year
- 4.1 days
- Activity to date
- 46.0 days
- Estimate to complete current year
- 14.3 days
- Estimate to complete future years
- 0.0 days