September 2015
- Report Date
- September 2015
Achievements in last period
- The outcome of the Sept meeting with all user represensatives has been the review and the sign off of the paid leave (maternity and sickness) processes to be and the related requirements.
Issues
- The two opened issues detailed in https://www.projects.ed.ac.uk/project/hrs084/issues/12 were not addressed during the Sept meeting as expected, due to lack of time.
- Paternity leave process to be and related 'must' requirement still need to be captured : https://www.projects.ed.ac.uk/project/hrs084/issues/14
Next Steps
- This will be followed by two further meetings in November to complete the sign off of the prioritised requirements and address both above issues .
19-Nov-2015 | Business Requirements Document reviewed and signed off |
30-Nov-2015 | Close |
- Approved budget
- 65.0 days
- Activity this month
- 2.3 days
- Activity this year
- 4.5 days
- Activity to date
- 57.0 days
- Estimate to complete current year
- 7.8 days
- Estimate to complete future years
- 0.0 days