August Report

Report Date
August 2015

Achievements in Last Period

  • Project stakeholders identified
  • High level project plan created
  • Project brief drafted and issued out for review by project team and project sponsor
  • Project brief review meeting held to estimate resource

 

Issues

  • Budget for project has been limited to 50 days following annual planning as advised by Project Sponsor
  • At project brief review it was agreed that this project should be reviewed by the Applications Architectural Group as there are a number of projects looking to complete similar deliverables e.g. SAC034 - Assessment and Progression in EUCLID and HSS are looking for interfaces to / from EUCLID.
  • Project team agree at a high level that the project estimate will be in the region of 70 days based on a similar project for the Library IDM Feed. This information has been passed to the Programme Manager and Project Sponsor to consider where additional funding can be acquired for the project.
  • Further clarity on business requirements needed to allow project brief to be submitted, Service Manager on leave however this information is now available to include in brief

 

 Next Steps

  • Planning and Resource Estimates
  • Project Brief approval

 

The project status is GREEN

 

11-Sept-15

Project Brief completed

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
50.0 days
Activity this month
4.2 days
Activity this year
5.1 days
Activity to date
9.3 days
Estimate to complete current year
45.7 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation

Not available.