August Report
- Report Date
- August 2015
Achievements in Last Period
- Project stakeholders identified
- High level project plan created
- Project brief drafted and issued out for review by project team and project sponsor
- Project brief review meeting held to estimate resource
Issues
- Budget for project has been limited to 50 days following annual planning as advised by Project Sponsor
- At project brief review it was agreed that this project should be reviewed by the Applications Architectural Group as there are a number of projects looking to complete similar deliverables e.g. SAC034 - Assessment and Progression in EUCLID and HSS are looking for interfaces to / from EUCLID.
- Project team agree at a high level that the project estimate will be in the region of 70 days based on a similar project for the Library IDM Feed. This information has been passed to the Programme Manager and Project Sponsor to consider where additional funding can be acquired for the project.
- Further clarity on business requirements needed to allow project brief to be submitted, Service Manager on leave however this information is now available to include in brief
Next Steps
- Planning and Resource Estimates
- Project Brief approval
The project status is GREEN
11-Sept-15 |
- Approved budget
- 50.0 days
- Activity this month
- 4.2 days
- Activity this year
- 5.1 days
- Activity to date
- 9.3 days
- Estimate to complete current year
- 45.7 days
- Estimate to complete future years
- 0.0 days