July 2015
- Report Date
- July 2015
Achievements in last period
- Completed the prioritisation of the mandatory requirements with Senior Users
Issues
- Project team cannot issue by email the requirements for approval by Senior Users as originally planned at beginning of August. There are conflicting views on some of the requirements, mostly on agreeing whether some of the fields are optional or mandatory. There are also been engagement issues with not all user groups being represented (https://www.projects.ed.ac.uk/project/hrs084/issues/11 and https://www.projects.ed.ac.uk/project/hrs084/issues/10) during the July meetings . It is proposed to sign off the requirements during an additional 2 meetings to be planned end August involving all senior users.
- This will affect estimates: more days from the technical implementation will be used for BA and PM times. To be estimated.
- This will also affect the project milestones: PM to revise dates once the 2 additional meetings have been scheduled.
Next Steps
- Complete /agree details of the prioritised MUST requirements
01-Sep-2015 | Business Requirements Document reviewed and signed off |
11-Sep-2015 | Close |
- Approved budget
- 55.0 days
- Activity this month
- 9.3 days
- Activity this year
- 52.7 days
- Activity to date
- 52.7 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 4.0 days