Monthly Progress Report

Report Date
June 2015

Achievements in last period:

  • Oracle TYE Bug Fix Patch tested in DEV
  • Oracle TYE Bug Fix Patch implemented to TEST
  • Oracle TYE Bug Fix Patch tested in TEST
  • HR Jar file work carried out in DEV
  • Agreed plan and milestone dates for HR Jar file for Test and Live
  • HR Jar file regression tested in DEV
  • HR Jar file work carried out in TEST
  • Oracle provided a work around for last TYE security patch
  • Oracle TYE work around security patch investigated and proven in Dev
  • Oracle TYE work around security patch now continuting via support under unidesk call  I150624-0740 as Payroll did not want the current plan affected with Go Live on Jul-6
  • HR Jar file regression tested in TEST, and signed off by HR and Payroll  - 2-Jul

Issues:

  • None

Next Steps:

  • HR Jar File and Oracle TYE Bug fix to proceed to Live on 6-Jul
  • Project Closure to be completed
  • Project to be closed

Milestones:

17-Jul-2015HR Jar File Live
31-Jul-2015Closure

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
110.0 days
Activity this month
6.2 days
Activity this year
95.6 days
Activity to date
95.6 days
Estimate to complete current year
5.7 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation

Not available.