June 2015
- Report Date
- June 2015
Achievements in last period
- Completed business requirements workshops with all 4 user groups: UHRS, College devolved HR, and both School and Support Groups
Issues
- Revised estimates, issue: new estimates are 50d (was 35d). Agreed 2d contingency will be used within the programme and 5 d from the HR Hesa project.
- Agreed milestones to move to 15/16 for the requirements sign offs and closure, to take into account the additional consultation work and holidays (https://www.projects.ed.ac.uk/project/hrs084/issues/7)
Next Steps
- Prioritise the mandatory requirements with Senior Users
- Complete some of the outstanding analysis and adress details of the prioritsed requirements
01-Sep-2015 | Business Requirements Document reviewed and signed off |
11-Sep-2015 | Close |
- Approved budget
- 35.0 days
- Activity this month
- 13.6 days
- Activity this year
- 43.5 days
- Activity to date
- 43.5 days
- Estimate to complete current year
- 3.7 days
- Estimate to complete future years
- 3.5 days