May 2015
- Report Date
- May 2015
Achievements in Last Period
- project initiation - done
- team resourced - done
- planning and resourcing - completed
Issues
- no issues of note
- no medium or high risks
Next Steps
- separate Edinburgh into its own environment
- TopDesk on-site to start analysis (end of June)
Milestones
| 30-Jun-2015 | Move the Edinburgh Database to its own Server |
| 10-Jul-2015 | Recommendations Report |
| 17-Jul-2015 | Project Closure |
- Approved budget
- 20.0 days
- Activity this month
- 1.0 day
- Activity this year
- 5.0 days
- Activity to date
- 5.0 days
- Estimate to complete current year
- 15.0 days
- Estimate to complete future years
- 0.0 days