May 2015
- Report Date
- May 2015
A final version of the recommendation report was discussed and was formally approved at meeting on 2nd June. it can then now be sent out to Senior Management by project sponsor.
Achievements in Last Period
- write report with recommentation for management - achieved
Issues
- no open issues or risks
Next Steps
- send report to management
- close project
Milestones
| 29-May-2015 | Recommendation after Visits to Institutions |
| 12-Jun-2015 | Closure |
- Approved budget
- 60.0 days
- Activity this month
- 5.0 days
- Activity this year
- 57.0 days
- Activity to date
- 57.0 days
- Estimate to complete current year
- 2.0 days
- Estimate to complete future years
- 0.0 days