Monthly Progress Report
- Report Date
- April 2015
Achievements This Period
- Brief has been completed
- Design document has been created
- Work related to the 2013-14 Archive had to be planned to be incorporated first into the HESA return this year.
- Replanned the Build and Acceptance Milestones to allow other Human Resources and Payroll & Pensions Projects to progress alonside the HESA Return
Issues
- None
Next Steps
- Design milestone approved
- Archive data for 2013-14 completed including adding the 3 new fields required for that archive year
- Once Archive data complete it will be carried forward through TEST and LIVE as soon as it can be, so that HR can complete the work required before the 2014-15 return moves to TEST.
- The majority of the Build work will be completed in May
Milestones
01-May-2015 | Design |
03-Jun-2015 | Initial Build |
26-Jun-2015 | Initial Acceptance |
31-Jul-2015 | Start of Deployment |
30-Sep-2015 | First HESA Return |
15-Oct-2015 | Commit |
12-Nov-2015 | Final Submission |
27-Nov-2015 | Closure |
- Approved budget
- 70.0 days
- Activity this month
- 8.4 days
- Activity this year
- 9.5 days
- Activity to date
- 9.5 days
- Estimate to complete current year
- 40.7 days
- Estimate to complete future years
- 19.9 days