January report
- Report Date
- January 2015
Achievements in last period
- Agreement for Development and Alumni to take ownership of the deployment of the Alumni Portal
- Handover to Development and Alumni
- Sponsor agreed for project to close, SSP agreed to pick up o/s issues in a small scale enhancement.
Issues
- Difficulty getting project sponsor to provide feedback for closure report https://www.projects.ed.ac.uk/project/sac025/issues/26
Next Steps
- Project close
Milestones
| Target date | Previous date | Title |
|---|---|---|
| 11-Feb-2015 | 29-Jan-2015 | Project close |
- Approved budget
- 157.0 days
- Activity this month
- 1.0 day
- Activity this year
- 22.0 days
- Activity to date
- 148.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days