Monthly Progress Report
- Report Date
- January 2015
January was a busy month accommodating the replanned Clone as well as the unplanned 4 fix patches. However due to IS Apps, Payroll & Pensions and HR this was accommodated in the planned timescales.
Achievements in last period:
- P1 RUP 7 DEV patching complete
- P1 RUP 7 DEV Testing complete
- P1 4 fix patches DEV complete
- Clone LIVE to TEST
- P1 4 fix patches DEV Testing complete
- P1 RUP 7 TEST patching complete
- P1 4 fix patches TEST patching complete
- P1 RUP 7 and 4 fix patches Acceptance complete
Issues:
- NOTE - As you can see from the achievements in January re 4 fix patches (1) and early notice below (2), some unplanned work was and may be required
- (1) - 4 fix patches had to be accommodated and the work has been signed off in P1 Acceptance testing.
- (2) - Early notice of potential patches for Shared Parental Leave for 2014-15, at present waiting confirmation from Oracle
Next Steps:
- P1 RUP 7 LIVE to be complete
- P2 TYE Planning patches
- P2 Planning Security patches
- P2 TYE DEV patches + Security patches
- P2 TYE DEV + Security patches testing
- P2 TYE TEST patches + Security patches
- P2 TYE ASOR + Security patches testing
Milestones:
04-Feb-2015 | P2 TYE Design/Planning Patching + Security |
05-Feb-2015 | P1 LIVE Pre-requisite patching |
17-Feb-2015 | P2 DEV TYE Patching + security patches |
02-Mar-2015 | P2 TEST/ASOR TYE Patching + security patches |
05-Mar-2015 | P2 LIVE TYE Patching + security patches |
16-Mar-2015 | P2 Dev P60 |
08-Apr-2015 | P2 TEST/ASOR P60 |
15-Apr-2015 | P2 LIVE P60 |
15-May-2015 | P3 Budget Design/Planinng (if req) |
22-May-2015 | P3 Budget DEV Patching (if req) |
05-Jun-2015 | P3 Budget TEST/ASOR Patching (if req) |
12-Jun-2015 | P3 Budget LIVE Patching (if req) |
15-Jul-2015 | Closure |
- Approved budget
- 130.0 days
- Activity this month
- 19.0 days
- Activity this year
- 33.0 days
- Activity to date
- 33.0 days
- Estimate to complete current year
- 94.0 days
- Estimate to complete future years
- 0.0 days