Report for January 2015

Report Date
January 2015

Achievements this Period

  • Continuing progress with TSM
  • Ongoing work on planning what needs to be decommissioned
  • Milestones for remainder of project established

Issues

  • Problems with TSM implementation in DEV

Next Steps

  • Work on analysing and cataloguing obsolete elements in infrastructure to be completed
  • Prioritisation of what is to be decommissioned to be carried out by project team
  • TSM to be implemented in DEV
  • TSM to be tested in TEST & LIVE
  • Password Manager deployment to be completed

Milestones

 

02-Feb-2015Planning (second phase) signed offAnalyse
05-Mar-2015TSM work completedBuild
02-Apr-2015Password Manager work completedBuild
07-May-2015Unix decommissioning (14-15) completedBuild
25-Jun-2015Windows decommissioning (14-15) completedBuild
02-Nov-2015Unix decommissioning (15-16) completedBuild
16-Nov-2015RedHat decommissioning (15-16) completedBuild
30-Nov-2015Recommendations and procedures signed offDeliver
07-Dec-2015Windows decommissioning (15-16) completedBuild
17-Dec-2015ClosureClose

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
253.0 days
Activity this month
21.1 days
Activity this year
44.3 days
Activity to date
44.3 days
Estimate to complete current year
108.7 days
Estimate to complete future years
100.0 days

Project Info

Not available.

Documentation

Not available.