Report for January 2015
- Report Date
- January 2015
Achievements this Period
- Server build completed
- Plesk software acquired and implemented
- Test migrations started
Issues
- None reported
Next Steps
- Migration process to be finalised
- List of sites and databases to be migrated completed
- Plans for migrations to be drafted
Milestones
| 11-Mar-2015 | Build stage sign-off | Build |
| 15-Apr-2015 | Integration sign-off | Integrate |
| 29-Apr-2015 | Acceptance sign-off | Accept |
| 04-May-2015 | Commence migrations to LIVE (Deployment milestone) | Deliver |
| 09-Jul-2015 | Deployment sign-off | Deliver |
| 17-Jul-2015 | Project closure | Close |
- Approved budget
- 161.0 days
- Activity this month
- 18.1 days
- Activity this year
- 45.8 days
- Activity to date
- 45.8 days
- Estimate to complete current year
- 113.4 days
- Estimate to complete future years
- 0.0 days