Report for January 2015

Report Date
January 2015

Achievements this Period

  • Server build completed
  • Plesk software acquired and implemented
  • Test migrations started

Issues

  • None reported

Next Steps

  • Migration process to be finalised
  • List of sites and databases to be migrated completed
  • Plans for migrations to be drafted

 

Milestones

11-Mar-2015Build stage sign-offBuild
15-Apr-2015Integration sign-offIntegrate
29-Apr-2015Acceptance sign-offAccept
04-May-2015Commence migrations to LIVE (Deployment milestone)Deliver
09-Jul-2015Deployment sign-offDeliver
17-Jul-2015Project closureClose

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
161.0 days
Activity this month
18.1 days
Activity this year
45.8 days
Activity to date
45.8 days
Estimate to complete current year
113.4 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation

Not available.