Report for December 2014

Report Date
December 2014

Achievements in Last Period

  • Last attempted at the email fix has been completed in Development with a plan to deploy to Test and Live in January.

Issues

  • Reported as Amber as every issue that has been fixed has highlighted another issue (since May 2014) so Application Support are not willing to close the project. Currently the issue preventing closure is implementing a  threshold check email.

Next Steps

  • Deploy threshold check to test and acceptance sign off
  • Deploy threshold check into live
  • Close the project

Milestones

 

 

07-Jan-2015Deploy email fix to Test
14-Jan-2015Deploy email fix to Live
21-Jan-2015Closure

 

Project Status
RAG Status
Overall
AMBER
Change Status
Activity
Approved budget
91.0 days
Activity this month
0.3 days
Activity this year
8.0 days
Activity to date
89.1 days
Estimate to complete current year
1.1 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation

Not available.