December update

Report Date
December 2014

 

  • Migrated TEST webcentral to new server
  • IS apps tested migrated app all ok
  • passed to Estates for UAT

 

  Issues

  • Due to holidays there has been limited testing to date.
  • project unrelated patch caused problems restarting app on test, which would also have caused problems in live.  - patch backed out of test/live

 

  Next Steps

  • sign off test environment next week
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
40.0 days
Activity this month
5.3 days
Activity this year
10.7 days
Activity to date
10.7 days
Estimate to complete current year
7.8 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation

Not available.