Report for December 2014

Report Date
December 2014

Achievements this Period

  • Deployment to LIVE signed off by stakeholders
  • DR testing carried out successfully on ne TEST environment
  • New DEV environment created and signed off

Issues

  • Additional effort required - to be discussed with Programme Manager

Next Steps

  • Project closure

Milestones

20-Jan-2015ClosureClose

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
136.0 days
Activity this month
23.0 days
Activity this year
142.3 days
Activity to date
147.2 days
Estimate to complete current year
2.0 days
Estimate to complete future years
0.0 days