November 2014
- Report Date
- November 2014
Achievements in Last Period
- Complete Questions, Answers and Scenarios for Visits - not achieved. Not all the team have made their contributions yet.
- Visit Sheffield in November - not achieved, but 16th december is confirmed
- Visit Imperial by early December - unlikely - waiting to hear
- Confirm third institution to visit by end of the Year - looking to visit Greenwich at same time as Imperial.
Issues
- Two Amber risks - last reviewed mid-November - no change and still pertinent
Next Steps
- Complete Questions, Answers and Scenarios for Visits
- Visit Sheffield in December
- Visit Imperial by end of January
- Confirm third institution to visit by end of January
Milestones
10-Dec-2014 | Prepare Questions and Model Answers |
09-Jan-2015 | Confirm Site Visits with other Institutions |
30-Jan-2015 | Optional - Visit a fourth institution write up outcomes |
30-Jan-2015 | Visit Three Institutions and write up outcomes |
27-Feb-2015 | Recommendation after Visits to Institutions |
13-Mar-2015 | Accepted Solution |
27-Mar-2015 | Closure |
- Approved budget
- 60.0 days
- Activity this month
- 4.0 days
- Activity this year
- 14.0 days
- Activity to date
- 14.0 days
- Estimate to complete current year
- 44.0 days
- Estimate to complete future years
- 0.0 days