Monthly Progress Report
- Report Date
- June 2014
Achievements this period
- DEA1 patch signed off in DEV, and Tested and Signed off in TEST 2-Jun
- DEA2 patch signed off in DEV, and Tested and Signed off in TEST 3-Jun
- RTI Fix signed off in DEV, and Tested and Signed off in TEST 3-Jun
- DEA1, DEA2 and RTI Fix deployed to LIVE on 7th July
- HMRC accepted Full Payment submission following LIVE updates and Direct Earnings process completed.
Issues
- None for HRS075
Next steps
- Project Closure
Milestones
Target Date | Title |
7-Jul-2014 | Direct Earnings Patch |
22-Jul-2014 | Project Closure |
- Approved budget
- 168.0 days
- Activity this month
- 6.0 days
- Activity this year
- 180.0 days
- Activity to date
- 180.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days