June 2014
- Report Date
- June 2014
Funded Budget
2012/13 overall funded budget (total, apps/service management) - 8 days (5/3) 2012/13 actual effort (total, apps/service management) - 8 days (3/5)
=
2013/14 overall funded budget (total, apps/service management) - 150 (105/45) 2013/14 actual effort (total, apps/service management) - 131 (112/ 19) So the project is delivering under 19 days of the funded budget approved by the UniDesk Project Board.
Overview
CMDB has been delivered to Edinburgh UniDesk and out partners and the project is now closed.
Milestones
| 05-Jun-2014 | Delivery of CMDB Process and Configured Database to Partners | Deliver | view |
| 12-Jun-2014 | Deployment Sign-Off | Deliver | view |
| 19-Jun-2014 | Project Closure | Close | view |
- Approved budget
- 108.0 days
- Activity this month
- 3.0 days
- Activity this year
- 110.0 days
- Activity to date
- 115.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days