June 2014

Report Date
June 2014

Funded Budget  

2012/13 overall funded budget (total, apps/service management) -      8 days  (5/3) 2012/13 actual effort (total, apps/service management)                   -      8 days  (3/5)

=

2013/14 overall funded budget (total, apps/service management) -  150 (105/45) 2013/14 actual effort  (total, apps/service management)                  -   131 (112/ 19) So the project is delivering under 19 days of the funded budget approved by the UniDesk Project Board.

Overview

CMDB has been delivered to Edinburgh UniDesk and out partners and the project is now closed.

 

Milestones  

05-Jun-2014Delivery of CMDB Process and Configured Database to PartnersDeliverview
12-Jun-2014Deployment Sign-OffDeliverview
19-Jun-2014Project ClosureCloseview

 

Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Activity
Approved budget
108.0 days
Activity this month
3.0 days
Activity this year
110.0 days
Activity to date
115.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days