Report for July 2014

Report Date
July 2014

Achievements This Period.

 
APPS migration to delivered.

Deployment signoff review achieved.

Closure questionnaires circulated.

Project Closed.

 

Issues

 

No issues

 

Next Steps

 

None

 

Milestones

 

 

1-Aug-2014Closure

 

 

The project RAG status is BLUE

Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Activity
Approved budget
194.0 days
Activity this month
16.0 days
Activity this year
200.0 days
Activity to date
200.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days