May Progress Report
- Report Date
- May 2014
Achievements this period
- Phase 3 Milestones withdrawn as agreed
- P60 to TEST
- Manual Business Workaround completed for May Payroll (The Direct Earnings patch was handled manually)
- P60 to LIVE
- HR Global in Dev completed successfully
- New Direct Earnings patch + HR Global + oracle fix applied to DEV (DEA1) -Successfully tested (last refresh in DEV was April)
Issues
- Although plan agreed for DEA, problems have already surfaced moving to TEST
- call has been raised with Oracle end of day 4-June - SR 3-8798535048
- discussion now taking place re a refresh of TEST (last refresh of TEST was Feb)
- contingency may be a manual solution again, but will depend on numbers
Next steps
- Plan agreed for the Direct Earnings Attachment changes (DEA2) (agreed 2-Jun)
- New Direct Earnings patch + HR Global + oracle bug fix (DEA1) to Test (plan 4-June)
- Payroll Testing out DEA1 (plan 5-6 June)
- DEA2 implementation plan patch to DEV (plan 4-Jun)
- DEA2 to TEST (plan 9-Jun)
- Payroll Testing out DEA2 (plan 9-11 June)
- DEA1 followed by DEA2 patch to LIVE (plan 12-Jun)
- Project Closure
Milestones
Target Date | Title |
13-Jun-2014 | Direct Earnings Patch |
27-Jun-2014 | Project Closure |
- Approved budget
- 168.0 days
- Activity this month
- 7.0 days
- Activity this year
- 165.0 days
- Activity to date
- 165.0 days
- Estimate to complete current year
- 8.0 days
- Estimate to complete future years
- 0.0 days