February 2014

Report Date
February 2014

Achievements in last period

  • Funding agreed for post live fixes
  • Post Live fixes built as per issue raised. Ready for deployment to Test

 

Issues

n/a

Next Steps

  • Test post live fixes and close

 

27-Mar-2014Post Live fix
24-Apr-2014Close

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
42.5 days
Activity this month
2.1 days
Activity this year
36.3 days
Activity to date
38.4 days
Estimate to complete current year
4.0 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation

Not available.