September 2013

Report Date
September 2013

Achievements in Last Period

  • Project Brief signed off

Issues

  • N/A

Next Steps

  • Complete refreshes of  Dev, Training, Test from LIVE

 

03-Oct-2013Refresh DEV from LIVE completed
09-Oct-2013Refresh TRN from LIVE completed
06-Nov-2013Refresh TEST from LIVE completed
06-Dec-2013Upgrade DEV to 8.7.0 completed
19-Dec-2013Testing upgrade to DEV reviewed
10-Jan-2014Upgrade TEST to 8.7.0 completed
14-Feb-2014Acceptance Review ASOR
03-Mar-2014Upgrade LIVE to v8.7.0 completed
17-Mar-2014Second Refresh of TEST from LIVE completed
17-Mar-2014LIVE Deployment review 1
31-Mar-2014Upgrade TRN to v8.7.0 completed
14-Apr-2014Deployment review 2
28-Apr-2014Close

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
150.0 days
Activity this month
15.8 days
Activity this year
17.2 days
Activity to date
17.2 days
Estimate to complete current year
132.0 days
Estimate to complete future years
0.0 days