Report for June
- Report Date
- June 2013
Achievements in Last Period
- Sign Off User Acceptance Testing
- Deploy to Live in early July
Issues
- Due to annual leave constraints the go live has been brought forward
Next Steps
- Handover to support and complete deployment checklist
Milestones
Target date | Title |
---|---|
25-Sep-2012 | Resume Project Work |
19-Oct-2012 | Estimates from Dev Team and Dev Tech |
05-Apr-2013 | Business Requirements Sign Off |
06-May-2013 | System Design Sign Off |
24-May-2013 | Peer Test Sign Off |
04-Jul-2013 | User Acceptance Test Sign Off |
08-Jul-2013 | Deploy to Live |
15-Jul-2013 | Deployment Sign Off Review |
17-Jul-2013 | Closure |
- Approved budget
- 61.0 days
- Activity this month
- 19.0 days
- Activity this year
- 49.0 days
- Activity to date
- 64.0 days
- Estimate to complete current year
- 12.0 days
- Estimate to complete future years
- 0.0 days