May Progress Report

Report Date
May 2013

Report by Anne Mathison for May 2013

 

Achievements in Last Period -

  • JRE Deployed on 6-May-13
  • Urgent A Pensions delivered 9-May-13
  • P3 Build RTI Changes and Security patches 13-May-13
  • P2 P60 issue with Oracle HR and Payroll resolved 20-May-13 (P60's arrived in households later that week)
  • P3 ASOR RTI Changes and Security patches 28-May-13
  • P3 Deploy RTI Changes and Security patches 3-Jun-13

 

Issues

  • There may be more RTI patches arriving in June
    • If so, they will have to be prioritised into their urgency, before deciding if have tf they should be deployed in 2012-13 or whether they can be handled in 2013-14.

 

Next Steps

  • RTI Inital Balances issue is being progessed by Finance/Payroll
    • Consultant will be on site to resolve the initial RTI Balances on 14th June.
    • Some new elements are to be set up.
    • After that Finance will run the RTI reports (through Dev,Test and Live) 
    • The pre-check alignment report will be sent to HMRC, when it is ready between the 6th and 25th June. HMRC will then notify us of any corrections
    • The final information is required by the June Payroll.
  • No confirmed patches for June at present.

 

Milestones

 

 

10-Jun-2013RTI Patches required by HMRC
31-Jul-2013Closure

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
165.0 days
Activity this month
17.0 days
Activity this year
160.0 days
Activity to date
160.0 days
Estimate to complete current year
13.5 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation

Not available.