Report for May 2013

Report Date
May 2013
  • Achievements in Last Period

Testing has progressed in TEST APPS environment  with both SACs and Service Management.

  • Issues

Some BO users will need re-pointed in TEST. App Management to progress.

SACS users unable to use Test MyEd users. Identity switch method used for this to allow testing.

  • Next Steps

Sign Off testing (ASOR)

Upgrade LIVE environment.

DSOR and Closure

 

Target dateTitle
12-Jun-2013ASOR
13-Jun-2013Deploy to LIVE - Upgrade LIVE Instance of APPS with EUPS Schemas
18-Jun-2013DSOR
21-Jun-2013Project Closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
27.0 days
Activity this month
0.5 days
Activity this year
20.0 days
Activity to date
25.4 days
Estimate to complete current year
1.6 days
Estimate to complete future years
0.0 days

Project Info

Not available.