Monthly Progress Report
- Report Date
- April 2013
Report by Anne Mathison for April 2013
Major issue this month is the resolution of the P60 which is legaily required for end on May.
The number of urgent patches and issues have required significantly more time than was expected to process and patch.
Achievements in Last Period -
- Phase 2 Deploy TYE and RTI Patches on 2nd April
- JRE and Password Change delivered to DEV on 3rd April, and to TEST 9th April
- JRE delivered to LIVE on 3rd May
Issues
- P2 P60 coded however had an issue and has been raised with Oracle, this is still ongoing and early in May a decision will be made as to when to increase the priority with Oracle to 24*7
- RISK 18 was raised surrounding this issue
- Second urgent unplanned Auto-enrolment Pensions work was required as soon as possible and had to be accommodated before the planned P3 RTI Changes and Security Patches began
- This then delayed the start of and reduced the time available for P3 RTI and Security work in Dev and Test
- LIVE planned date is unchanged.
- Auto-enrolment continues to have patches arriving that require to be accommodated and the planned work re-planned
- There has already been notifications of more RTI patches arriving in June after P3 is complete
- These will have to be prioritised before planning more new work
- Project estimates have been reviewed and revised estimate requires agreed.
Next Steps
- P2 P60 issue with Oracle. HR and Payroll require P60 to be resolved before May 19th.
- P3 Build RTI Changes and Security patches
- P3 ASOR RTI Changes and Security patches
- P3 Deploy RTI Changes and Security patches
Milestones
06-May-2013 | JRE and Password change |
09-May-2013 | Urgent AE Pensions Milestone |
13-May-2013 | 3 Build RTI Changes + Security patches |
19-May-2013 | 2 P60 Live |
28-May-2013 | 3 ASOR RTI Changes + Security Patches |
03-Jun-2013 | 3 Deploy RTI Changes + Security |
31-Jul-2013 | Closure |
- Approved budget
- 165.0 days
- Activity this month
- 16.0 days
- Activity this year
- 142.0 days
- Activity to date
- 142.0 days
- Estimate to complete current year
- 36.0 days
- Estimate to complete future years
- 0.0 days