Report for March

Report Date
March 2013

Achievements in Last Period

  • Build complete and deployed to Test
  • Acceptance Testing commenced

Issues

  • Slight delay due to clarification in requirement may need to revise go live if any overrun in Acceptance Testing.

Next Steps

  • Complete Acceptance Testing
  • Deploy to Live

Milestones

 

14-Jan-2013End of Planning - complete
28-Feb-2013Requirements Sign Off - complete
08-Mar-2013Design Review - complete
25-Mar-2013Build Review - complete
05-Apr-2013Acceptance Test Sign Off
08-Apr-2013Go Live
15-Apr-2013Deployment Sign Off
19-Apr-2013Close

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
45.0 days
Activity this month
5.6 days
Activity this year
38.6 days
Activity to date
38.6 days
Estimate to complete current year
6.1 days
Estimate to complete future years
0.0 days