March Report

Report Date
March 2013

Report by Anne Mathison for March 2013

Achievements in Last Period -

  • Release to TEST re Phase 2 TYE & RTI completed 5th March
  • UAT for Phase 2 for TYE & RTI completed on 6-7th March
    • UAT was not signed off by the Business due to some payroll processing occurring twice, so the Go Live planned for 11-12th March was cancelled and delayed until issues were sorted.
    • Rescheduled for later in March
  • Milestones and estimates revised for remaining Phase 2 pieces of work
  • P2 TYE & RTI signed off in LIVE 27th March.  
  • Unplanned Urgent AE Patch required. Completed in DEV on 27th March and signed off 27th March
  • Unplanned Urgent AE Patch required. Completed in TEST on 28th March and signed off on 29th March
  • Unplanned Urgent AE Patch required. Completed in LIVE on 1st April and signed off on 1st April

 

Issues

  • P2 P60 coded however had an issue  and has been raised with Oracle
  • First unplanned Auto-enrolment work was required as soon as possible and had to be accommodated before the tight P2 TYE + RTI patches deadlines.
    • This then reduced the time available for TYE + RTI in Dev and Test
    • Separating out and replanning the P2 Security patches
    • Delaying implementing the P60 work
  • Original TYE & RTI work was delayed deploying to LIVE from 11th-12th March to 26-27th March
  • HR Globals caused errors when completing patches, however this was resolved in time for the go LIVE implementation  of TYE & RTI on 26-27 March.
  • Unplanned Urgent TYE + RTI required patch arrived 25-Mar-13 also required for Phase 2 go LIVE - was progressed after the TYE & RTI on 26-27 March and progressed in time to go LIVE 1st April

 

Next Steps

  • P2 P60 with Oracle, hope to have resolved during April - no down time required.
  • P3 JRE patches and Password change scheduled for April, DEV 3rd April, TEST 9th April and LIVE 2nd May.
  • P3 more RTI patches and Security Patches planned during May

 

Milestones

 

02-Apr-20132 Deploy TYE and RTI Patches plus Urgent AE Patch
30-Apr-20132 P60 Live
03-May-2013JRE and Password change
09-May-20133 Build RTI Changes + Security patches
28-May-20133 ASOR RTI Changes + Security Patches
03-Jun-20133 Deploy RTI Changes + Security
31-Jul-2013Closure

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
165.0 days
Activity this month
29.0 days
Activity this year
126.0 days
Activity to date
126.0 days
Estimate to complete current year
43.0 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation

Not available.