December/January Progress
- Report Date
- January 2013
Achievements in Last Period
- Both Clones completed
- Phase 1 Acceptance Testing had some issues and was signed off late, but just in time to enable Phase 1 to go LIVE as planned.
- Phase 1 Family Pack and Auto-enrolment went LIVE as planned (24-25th Jan-13).
Issues
- Phase 2 delayed by Oracle
- Oracle Tax Year End (TYE) patches released 1st Feb, work for Phase 2 re-planned to start 11th Feb.
Next Steps
- Investigation into Phase 2 Tax Year End (TYE), Real Time Information (RTI), P60, JRE and Security Patches
- Build for Phase 2 TYE, RTI, P60, JRE and Security Patches is planned to be completed
- Release to Test Phase 2 for TYE, RTI JRE and Security Patches
- Approved budget
- 148.0 days
- Activity this month
- 44.0 days
- Activity this year
- 53.0 days
- Activity to date
- 53.0 days
- Estimate to complete current year
- 91.0 days
- Estimate to complete future years
- 0.0 days