Report for September 2012

Report Date
September 2012

Achievements in Last Period

The Showstopper issue of last month (file transfer issues) was successfully resolved

The project was brought to a position where the build was complete and ready to be re-peer tested.

Issues

Following a meeting on 13 Sept with Bryan MacGregor and Maurice Franceschi, it was decided to stop the project because it was clear additional budget would be required to progress with integration testing, UAT, deployment etc - a breakdown of the remaining estimated effort was sent to Bryan.

Next Steps

In agreement with Bryan MacGregor, one day of effort (maximum) is to be spent to complete peer testing and  close the project. This will mean that the project should close having used 125 days (out of an approved budget of 125 days).

Milestones

 

Target dateTitle
14-Aug-2012DSOR : Phase 1 DSOR milestone achieved
17-Sep-2012Deployment - CANCELLED
17-Sep-2012Integration - Phase 2 - CANCELLED
17-Sep-2012Accceptance Phase 2 - CANCELLED
10-Oct-2012Phase 2 Build - Complete Peer Test
16-Oct-2012Closure

 

Project Status
Activity
Approved budget
125.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
124.7 days
Estimate to complete current year
0.3 days
Estimate to complete future years
0.0 days