Report for August 2012
- Report Date
- August 2012
Report for August 2012
Achievements in Last Period
- Acceptance Testing was signed off
- An urgent fix was required in Live for an OLL student. The fix was completed in HESA for this student.
Issues
- The duplicate OLL Student was resolved in the HESA tables. This was resolved during late August.
Next Steps
- As data and fixes for HESA continue to be clarified the return continues to be run regulary to see if HESA find it satisfactory or have identified new problems.
- Although OLL are able to complete a clean OLL return at present, it will depend on feedback from HESA how many times the HESA combined return has to have data and /or changes to pass the HESA validation as HESA amend it. The combined return cannot be committed and the project closed until the combined return has beeen signed off by HESA. This means that the project will remain open until that time (which could be as late as the end of October).
- The return has been committed and we are now waiting to see if our explanations are satisfactory, if not we will have to run the return again
Target date | Title |
---|---|
31-Oct-2012 | Closure |
31-Oct-2012 | Combined credible clean return signed off |
- Approved budget
- 72.0 days
- Activity this month
- 8.0 days
- Activity this year
- 8.0 days
- Activity to date
- 67.0 days
- Estimate to complete current year
- 4.0 days
- Estimate to complete future years
- 0.0 days