Report for August 2012
- Report Date
- August 2012
Achievements in Last Period
Peer testing was carried out to plan
Issues
- There are 4 outstanding Jiras which were raised during peer testing, one of which is a show-stopper. This meant that the PPBR meeting could not be held.
- The key developer has been moved to another project but is available during w/c 10 Sept for 3 days. It is hoped that this will be sufficient to resolve the outstanding Jiras. There is a concern that the show-stopper Jira (transfer of image file) is an unknown amount of effort. A resource from dev tech is to be made available to support the resolution of this issue.
- The unplanned additional effort to resolve the Jiras and re-test means that the budget for the project is likely to increase again (likely to be around an additional 6 days taking it to a total of 131 days). This has not yet been approved by USD.
- USD has hinted at aborting the project but the image upload functionality is required for the Personal Tutor project therefore it is preferable that the project can achieve PPIR as a minimum.
Next Steps
Resolve the outstanding Jiras and peer test. Endeavour to move the project into the test environment
Milestones
The milestones are based on the Jira's being completed during the w/c 10 Sept. If this is not achieved then the milestones will need to be revised.
Target date | Title |
---|---|
14-Aug-2012 | DSOR : Phase 1 DSOR milestone achieved |
12-Sep-2012 | Phase 2 Build - PPBR |
27-Sep-2012 | Integration - Phase 2 |
21-Dec-2012 | Accceptance Phase 2 |
31-Dec-2012 | Deployment |
04-Jan-2013 | Closure |
- Approved budget
- 125.0 days
- Activity this month
- 8.0 days
- Activity this year
- 0.0 days
- Activity to date
- 119.0 days
- Estimate to complete current year
- 13.0 days
- Estimate to complete future years
- 0.0 days