Report for August 2012

Report Date
August 2012

Achievements in Last Period

Peer testing was carried out to plan

Issues

  • There are 4 outstanding Jiras which were raised during peer testing, one of which is a show-stopper. This meant that the PPBR meeting could not be held.
  • The key developer has been moved to another project but is available during w/c 10 Sept for 3 days.  It is hoped that this will be sufficient to resolve the outstanding Jiras. There is a concern that the show-stopper Jira (transfer of image file) is an unknown amount of effort. A resource from dev tech is to be made available to support the resolution of this issue.
  • The unplanned additional effort to resolve the Jiras and re-test means that the budget for the project is likely to increase again (likely to be around an additional 6 days taking it to a total of 131 days). This has not yet been approved by USD.
  • USD has hinted at aborting the project but the image upload functionality is required for the Personal Tutor project therefore it is preferable that the project can achieve PPIR as a minimum.

Next Steps

Resolve the outstanding Jiras and peer test.  Endeavour to move the project into the test environment

Milestones

The milestones are based on the Jira's being completed during the w/c 10 Sept.  If this is not achieved then the milestones will need to be revised.

Target dateTitle
14-Aug-2012DSOR : Phase 1 DSOR milestone achieved
12-Sep-2012Phase 2 Build - PPBR
27-Sep-2012Integration - Phase 2
21-Dec-2012Accceptance Phase 2
31-Dec-2012Deployment
04-Jan-2013Closure

 

Project Status
Activity
Approved budget
125.0 days
Activity this month
8.0 days
Activity this year
0.0 days
Activity to date
119.0 days
Estimate to complete current year
13.0 days
Estimate to complete future years
0.0 days

Project Info

Not available.