Weekly update w/c 19/08/13

  • The last of the eIT enhancements is now complete and has been deployed to the Test system
  • FIS have been requested to test the eIT enhancements but they are currently struggling to allocate any time to this.  This has been flagged to the project sponsor.
  • As soon as this last workpackage is installed into live the project will move to closure
  • The draft closure report has been started