Report for June 2014

Report Date
June 2014

Nikki Stuart (IS Apps Portfolio Manager) for Bruce Nelson (Portfolio Owner) 

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

Section One: Programme Commentary, RAG and Resources Update

 

Commentary

 

SCE002 Tomography Control - Closed - upon LIVE running deliverables exceeded success criteria set at the start of the project. 

SCE003 Path Enhancements - GREEN -  Build review complete and preparations to allow testing to start underway. 

SCE004 University Seminar Site - AMBER - Completion of build tasks delayed due to the developers Paternity leave and the Sponsors availability. Project has been replanned and requires some work to be completed in 14/15, Milestones and budget still to be agreed with Sponsor and Portfolio Owner.  

 

 

 

 

 Section Two: Projects Not Started

 

Project InfoProgramme Manager's Commentary

SCE Ring fenced days

 
  

 

 

Section Three: Projects in Progress

 

Project InfoProject Managers Commentary

 SCE003 - PATH Enhancements

 

 

Category: Discretionary, IS Funded

 

Milestones

 
18-Jul-2014Acceptance sign off
28-Jul-2014Deploy to Live
11-Aug-2014Deployment sign off review DSOR
25-Aug-2014Close

RAG Status

GREEN

Report by Franck Bergeret for June 2014

Achievements in last period

 

 
  • Build reviewed

  • New Test environment available
  • Integration reviewed

Issues

 

  • n/a

Next Steps

 

  • User testing

  • Deploy to Live

 

 

SCE004 - University Seminar Site

 

 

Category: Discretionary, Core Funded

 

Milestones

(The milestones reported below are what have been submitted

to WIS for authorisation and still need to be agreed with the Portfolio Owner)

 

RAG Status

AMBER

Report by Sally Hayward for June 2014

Achievements in Last Period

  • Some issues with the DEV environment have been resolved.
  • Project Sponsor shown a preliminary view of the new site
  • Brief submitted to WIS 6/6/2014

Issues

  • The allocated developer's paternity leave was earlier than originally planned and the combination of both project and business annual leave has contributed to a delay in the planned milestones.
  • The project will now require some effort to be arried over to the 14/15 academic year.

Next Steps

  • Obtain complete sign-off for Milestone delays and carry-over
  • Complete sign-off of the TAD
  • Complete the testing and sign-off of the DEV environment

 

Section Four: Closed or Withdrawn Projects

 

Project InfoProject Managers Commentary

  

Project Code 

SCE001

Project Title

 PATH

 

Category

 

Report by Franck Bergeret 

 

 

SCE002 Tomography Control 

 

 

Programme Info

Not available.