Report for May 2014
- Report Date
- May 2014
Nikki Stuart (IS Apps Portfolio Manager) for Bruce Nelson (Portfolio Owner)
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Commentary
SCE002 Tomography Control - GREEN -
SCE003 Path Enhancements - GREEN - Design sign off agreed and environments established to allow build to start.
SCE004 University Seminar Site - GREEN - Briaf agreed and build underway.
SCE Portfolio Manager has provided feedback to the SCE Portfolio Owner on proposed pieces of work for 13/14 projects and onwards, 20 days ring fenced allocated has been held against the Portfolio for 14/15 planning.
Projects of interest in other programmes or portfolios;
Timetabling Programme (https://www.projects.ed.ac.uk/programme/ttu) - 'MyTimetable' - Personalised Timetables for Taught Students (via MyEd) went live in August 2013
eRecruitment Phase 2 (Talent Pool), LIVE deployment planned for May 2015. This project will allow the University to benefit from enhanced functionalityby including a major upgrade to the software in the project.


Section Two: Projects Not Started
| Project Info | Programme Manager's Commentary |
SCE Ring fenced days | |
Section Three: Projects in Progress
| Project Info | Project Managers Commentary | ||||||||||||||||||
SCE002 Tomography Control Category: Discretionary, Funded
Milestones
RAG Status GREEN | Report by Dave Berry for April 2014Achievements in Last PeriodProject delivered. The performance of the system has exceeded expectations IssuesThere is one minor issue that the project sponsor wishes to investigate further. As the project sponsor is not in Edinburgh until mid-May and there is no support budget for this system, the closure has been put back until the end of May. Next StepsIf necessary, produce a fix for the issue noted above. Then proceed to closure. | ||||||||||||||||||
Category: Discretionary, IS Funded
Milestones
RAG Status GREEN | Report by Franck Bergeret for May 2014 Achievements in last period
Issues
Next Steps
| ||||||||||||||||||
SCE004 - University Seminar Site
Category: Discretionary, Core Funded
Milestones
RAG Status GREEN | Report bySally Hayward for May 2014 Achievements in Last Period
Issues None Next Steps
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
Project Code SCE001 Project Title PATH
Category
| Report by Franck Bergeret
|