Programme Report for September 2012
- Report Date
- September 2012
Report compiled by Maurice Franceschi (IS Apps Programme Co-ordinator) for Jared Taylor (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Programme Owner and Manager have agreed on a re-prioritisation of projects and budgets to match.
Accordingly, the Infrastructure project will now go ahead, immediately, followed by an in-year proejct of Portal Enhancements, and if time and budget remain a (descoped) MyGroups.
WIS rejected the proposed changes, so the ASTA summary does not reflect the actual planning. Hope to have the situation clarified to WIS by 12th October.
We expect :-
Summary of funding moves:
| Project | Before | After | Notes |
| TELP03 Planning for Projects | 9 | 9 | |
| AP23-033 ECA Portal My Groups | 116 | 0 | Suspended Last project |
| ECA001 Infrastructure | 57 | Restarted First Project | |
| TELPB3 Balance Row | 34 | 93 | To be used for in year project enhancements to exam boards and descoped My Groups. Second Project |
| Programme Total / Baseline | 159 | 159 |
In order to do as much as possible this year, PM and PgM met with technical leaders and we will now port ECA onto a CF9/SQL Server configuration instead of converting to Oracle. This will save us about 30 days from the 75 day budget.
Actions from programme meeting


Section Two: Projects Not Started
| Project Info | Programme Manager's Commentary |
AP23-033 ECA Portal My Groups ECA Ring-Fenced Milestones TBC
RAG Status Amber | Plan Other work has risen in priority which probably lead to this proposal being descoped or even withdrawn. It wil be reviewed once Infrastructure Project and in-year Enhancements have delivered.
Dependencies None |
Section Three: Projects in Progress
| Project Info | Project Managers Commentary | ||||
ECA001 ECA Portal Infrastructure Category: Essential Milestones
RAG Status Amber | Achievements in Last Period
|
Section Four: Projects Closed / Withdrawn
| Project Info | Project Managers Commentary |
Actions from September Programme Meeting (TBC)
Actions from August Programme Meeting (19th Sept)
| ) Craig to pick up Infrastructure project - if not possible Maurice to get another project manager. Right away. | Craig Maurice | Done - Craig is PM |
Jared will work with colleagues on an analysis of the portal content and triage content that is not being updated content that resides on the university website - remove from Portal? Or link from Portal? Content that is best kept in the portal
And where from Website do we link back to portal, and consider a MyED launcher
And ECA to commit to maintianing the
I think that if at the end of the exercise ECA could articulate their vision for the portal in the medium term ... more than an VLE, just a VLE, the main resource from where students start ... it would help | Jared ECA | Pending |
Craig to organise an estimation meeting with John A. so we can get a rough budget for the enhancements for the board : project to eb set up with delivery date April | Craig | Pending |
Need to chunk up the My Groups requirements and focus on the highest priority - List of Groups for example. After 1) and 2) and 3) are done, then whatever budget is left will be prioritised for My Groups. Do we already have this requirements/task breakdown? | Jared | Pending |