Programme Report for September 2012

Report Date
September 2012

 

Report compiled by Maurice Franceschi (IS Apps Programme Co-ordinator) for Jared Taylor  (Programme Owner)

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

 

Section One: Programme Commentary, RAG and Resources Update

Programme Owner and Manager have agreed on a re-prioritisation of projects and budgets to match.

Accordingly, the Infrastructure project will now go ahead, immediately, followed by an in-year proejct of Portal Enhancements, and if time and budget remain a (descoped) MyGroups.

WIS rejected the proposed changes, so the ASTA summary does not reflect the actual planning. Hope to have the situation clarified to WIS by 12th October.

We expect :-

 

Summary of funding moves:

 

ProjectBeforeAfterNotes
TELP03 Planning for Projects99 
AP23-033 ECA Portal My Groups1160

Suspended

Last project

ECA001 Infrastructure 57

Restarted

First Project

TELPB3 Balance Row3493

To be used for in year project enhancements to exam boards and descoped My Groups.

Second Project

    
Programme Total / Baseline159159 

 

In order to do as much as possible this year, PM and PgM met with technical leaders and we will now port ECA onto a CF9/SQL Server configuration instead of converting to Oracle. This will save us about 30 days from the 75 day budget.

Actions from programme meeting

 

 

 

 

 

 Section Two: Projects Not Started

Project InfoProgramme Manager's Commentary

AP23-033

ECA Portal My Groups ECA Ring-Fenced  

Milestones

TBC

 

RAG Status Amber  

Plan Other work has risen in priority which probably lead to this proposal being descoped or even withdrawn. It wil be reviewed once Infrastructure Project and in-year Enhancements have delivered.

Proposal and Estimates

 

Dependencies None

  

 

Section Three: Projects in Progress

Project InfoProject Managers Commentary

ECA001

ECA Portal Infrastructure

Category: Essential

Milestones

 

Target dateTitle
25-Sep-2012Resume Project Work

RAG Status

Amber

Achievements in Last Period
  • Project Prioritised as Top Project in the ECA progamme with an ideal delivery date in December 2012
Issues
  • Dev Team are unavailble to commence work until October due to other priorities
  • Need to make a final decision on the Infrastrucutre to opt (i.e. Oracle vs MS Sql Server)
Next Steps
  • Re-estimate the remaining work and transfer budget from the ECA 2012/13 budget
  • Make final decision on which was to take the infrastructure
  • WIS to agree budget increase for migration work

 

Section Four: Projects Closed / Withdrawn

 

Project InfoProject Managers Commentary
  

 

Actions from September Programme Meeting (TBC)

 

Actions from August Programme Meeting (19th Sept)

) Craig to pick up Infrastructure project - if not possible Maurice to get another project manager. Right away.Craig MauriceDone - Craig is PM

Jared will work with colleagues on an analysis of the portal content and triage content that is not being updated content that resides on the university website - remove from Portal? Or link from Portal?

Content that is best kept in the portal

 

And where from Website do we link back to portal, and consider a MyED launcher

 

And ECA to commit to maintianing the

 

I think that if at the end of the exercise ECA could articulate their vision for the portal in the medium term ... more than an VLE, just a VLE, the main resource from where students start ... it would help

Jared ECAPending

Craig to organise an estimation meeting with John A. so we can get a rough budget for the enhancements for the board : project to eb set up with delivery date April

CraigPending

Need to chunk up the My Groups requirements and focus on the highest priority - List of Groups for example. After 1) and 2) and 3) are done, then whatever budget is left will be prioritised for My Groups. Do we already have this requirements/task breakdown?

JaredPending

 